249 Project information Short project description Nemetschek Engineering User Contest 2011 - Category 5: Special Projects Category 5: Special Projects 5 Owner Geosea (Belgium) General Contractor G&G International (Belgium) Engineering Office Temporary Work Design BV Construction Period From November 2009 to April 2010 Location Irish Sea, United Kingdom The project concerns the design of a piling template for the Ormonde wind farm in the Irish Sea (UK), built by offshore contractor GeoSea. For fast and accurate installation of the foundation piles a ‘piling template’ is used. GeoSea requested Temporary Works Design to make a design for this template, from concept to detailed drawings. The strength of both the global design and local details are checked with1D and 2D models built in Scia Engineer. Several auxiliary equipment items (such as winch foundations, hammer sea fastening supports and access bridges) are designed with Scia Engineer as well. Piling Frame for Ormonde Wind Farm Irish Sea, United Kingdom