83 Project information Short project description Nemetschek Engineering User Contest 2011 - Category 1: Buildings Category 1: Buildings 1 Owner Land Salzburg Architect Domenig und Wallner Engineering Office ZT TOMS Construction Period From January 2010 to January 2012 Location Zell am See, Austria The project is about the embellishment, the large scale modification as well as a new building of the general public hospital Zell am See. The new building consists of 2 elongated four-storeyed buildings. The construction is made of reinforced concrete. The ceilings are planned without beams as far as possible, that is why the installation of the building can be easier fixed. The buildings are connected with bridges at each floor. For the foundation plan was used a foundation by ductile ram piles. With Scia Engineer, the concept of the foundation could be planned close to reality and economically. General Public Hospital Zell am See, Austria