            Category 4: Special Projects
          
        
        
          
            4
          
        
        
          
            Owner
          
        
        
          
            Enseada Industria Naval S.A.
          
        
        
          
            Architect
          
        
        
          
            Gusto MSC / ICE - Inernational Contract
          
        
        
          
            Engineering
          
        
        
          
            General Contractor
          
        
        
          
            Construtora Norberto Odebrecht S.A.
          
        
        
          
            Engineering Office
          
        
        
          
            Odebrecht Engenharia Industrial
          
        
        
          
            Construction Period 06/2013 - 07/2016
          
        
        
          Paraguaçu Unit is building six drillships for Sete Brasil. The equipment
        
        
          will be used in the exploration of pre-salt deposits, at a depth of three
        
        
          thousand meters. Four of these ships - Ondina, Pituba, Boipeba and
        
        
          Interlagos - are being built in partnership with Odebrecht Óleo e Gás.
        
        
          The other two - Itapema and Comandatuba - involve another partnership:
        
        
          Etesco/OAS. The total value of the contract is around US$ 4.8 billion.
        
        
          Due to the upside-down construction methodology adopted, the
        
        
          Megablocks structure needed to be verified during the upending
        
        
          operation. This analysis was performed in SCIA Engineer by means of
        
        
          a Finite Element model. The Megablocks structure was modeled with
        
        
          shell elements (2D) and the cables used in the lifting arrangement were
        
        
          modeled with frame elements (1D).
        
        
          The load during the upending operation is the self-weight of Megablocks,
        
        
          approx. 100 tons, based on information given by the architect. Yielding
        
        
          and linear buckling, based on static linear elastic calculation, have
        
        
          been verified. From these analyzes, local reinforcements were added,
        
        
          because of high stresses in the lifting system. These reinforcements were
        
        
          developed and verified with the help of SCIA Engineer, ensuring safe
        
        
          operation.
        
        
          
            
              Lifting of Megablocks - Maragojipe Bahia, Brazil
            
          
        
        
          
            SE
          
        
        
          
            Contact
          
        
        
          
            Debora Coting
          
        
        
          
            Address Rua Lemos Monteiro, 120
          
        
        
          
            12th floor
          
        
        
          
            Butantã, São Paulo, Brazil
          
        
        
          
            Website 
          
        
        
        
          Odebrecht is a Brazilian organization composed of diverse businesses
        
        
          with global operations and quality standards. Through its leading
        
        
          companies Odebrecht serves the following industries: Engineering and
        
        
          Construction, Investment in Infrastructure and Energy, Industry and
        
        
          Auxiliary Institutions. The company generated 7,000 direct jobs through
        
        
          the Consórcio Estaleiro Paraguaçu (CEP) consortium, which was hired to
        
        
          build the Enseada’s shipyard, one of the world’s most modern shipyards.
        
        
          
            Construtora Norberto Odebrecht