 
          164
        
        
          
            X2
          
        
        
          
            Category 2: Civil Structures
          
        
        
          
            Project description
          
        
        
          Ceintuurbaan Station is part of the North/South line
        
        
          project, situated in the historic centre of Amsterdam.
        
        
          The scope of the project contains eight stations and
        
        
          connects the northern and southern districts with the
        
        
          city centre.
        
        
          The metro line measures approximately 10 km in length,
        
        
          divided into an underground section of 7 km and a
        
        
          bored tunnel of 3 km long. The metro line runs from the
        
        
          above-ground Buikslotermeerplein Station via a semi-
        
        
          sunken route and is connected with the Central Station
        
        
          by an immersed tunnel below the IJmeer. From the
        
        
          Central Station, the metro line continues its route via the
        
        
          stations Rokin, Vijzelgracht and Ceintuurbaan. These
        
        
          stations are all constructed at an average depth of 30 m
        
        
          below the surface and are connected by a bored tunnel.
        
        
          At Europaplein Station the metro arrives above the
        
        
          ground and is connected to the existing metro network
        
        
          at Zuid/WTC Station.
        
        
          
            Structure and building method
          
        
        
          Ceintuurbaan Station is 230 m long and has an average
        
        
          width of 11 m. Due to the limited space available
        
        
          between the buildings at street level, the station is
        
        
          designed for two bored tunnels, which are located
        
        
          above each other. The station has two main entrances
        
        
          through which passengers can enter the station at
        
        
          NAP +0.6 m.
        
        
          From the concourse level at NAP -6.8 m, passengers
        
        
          (approximately 42,500 a day) are divided over the two
        
        
          lower platforms by an escalator or elevator.
        
        
          To minimise the duration of the impact on traffic and
        
        
          the surroundings, the station is built by using the cut &
        
        
          cover method. First, the diaphragm walls, 1.2 m thick,
        
        
          and the roof were made. Below the roof structure more
        
        
          excavation took place, while constructing several floors
        
        
          and metro platforms. To guarantee the vertical stability
        
        
          of the deepest section, the last couple of metres were
        
        
          excavated under compressed air, starting from the
        
        
          intermediate floor at NAP -18.8 m. After the completion
        
        
          of the foundation slab, the concrete structure was ready
        
        
          to be connected with the bored tunnels.
        
        
          
            Horizontal stability of the structure
          
        
        
          During the excavation process, the diaphragm walls
        
        
          were supported by temporary steel struts at different
        
        
          levels to secure horizontal stability. Due to its great
        
        
          depth and the presence of several openings in the floor
        
        
          slabs, the combination of diaphragm and retention walls
        
        
          also has to be supported by additional struts in the final
        
        
          phase. These struts are applied at five different levels.
        
        
          The permanent steel struts are installed and
        
        
          prestressed in the presence of the temporary steel
        
        
          struts and floor slabs. The temporary steel struts are
        
        
          removed in different phases. During removal, the
        
        
          deflection of the steel struts is monitored by strain
        
        
          gauges and extensometers. With the information
        
        
          obtained from these measuring instruments, the forces
        
        
          per construction stage can be determined.
        
        
          
            Use of Scia Engineer
          
        
        
          To verify these results, a 3D model of the station is
        
        
          created in Scia Engineer. With the use of the module
        
        
          ‘construction stages’, the influence of the several
        
        
          construction phases could be predicted. This gave the
        
        
          opportunity to verify the retrieved information from the
        
        
          monitoring. Furthermore, the model made it possible to
        
        
          anticipate critical situations and to prevent the forces
        
        
          from exceeding the design values in the consecutive
        
        
          stages.
        
        
          
            Software: Scia Engineer
          
        
        
          
            Ceintuurbaan Station, North/South Metro Line - Amsterdam, The Netherlands